Your $180K Project Is Losing Money and You Don't Even Know It

Tax-Saving Video Series · With Samy Basta, CPA

In this episode, Samy explains why so many contractors work six days a week and still wonder where the money went. He tells the story of a $3 million construction firm that believed it ran at about 15% profit, until two weeks of project tracking in QuickBooks showed its $180,000 flagship job was losing about $9,000. Then he lays out three steps and three numbers that turn your books into a project-by-project scoreboard.

Jump to: Episode insights · The three steps · The $180K project

Lightly edited for readability: speech-to-text errors corrected, wording unchanged.

 

Most contractors I talk to are working six days a week and still wondering where all that money went. You’re booked, you’re busy, your phone doesn’t stop, but at the end of the month, the bank account tells a different story. That’s not a hustle problem. That’s a profit leak problem.

 

So here’s the hard truth. Most contractors have no idea which projects are making them money and which projects are quietly stealing it.

 

For example, I met with a construction firm owner recently. $3 million a year in revenue, great reputation, tons of work. And when I asked him how profitable he was, he said around 15%. Very confident. So we set up a simple tracking system in QuickBooks. Two weeks later, I sent him the report. He called me, and he was kind of upset, because one of his biggest projects, a $180,000 contract he was proud of, was actually losing money. It was losing about $9,000 after labor, materials, and subs. He wasn’t doing anything wrong. He just didn’t have a system that told him the truth.

 

That’s the real problem. Most construction businesses run as one big pile of numbers. Revenue in, expenses out. Nobody really knows which project won and which project lost. So let me give you three steps to fix this.

 

Step one: give every project its own scoreboard. In QuickBooks, this is called a project. Every contract gets its own file, and every dollar you spend, whether it’s labor, materials, subs, permits, or equipment rental, gets tagged to that project. If you spend money because of that contract, it belongs there. This one change turns your books from a black box into a scoreboard.

 

Step two: review it every week. Just 10 minutes. Open your project profitability report, sort by profit, look at your bottom three projects, and ask one question: why is this project losing money? Usually it’s one of four things. Either labor went over, materials weren’t tracked right, a subcontractor added scope, or you forgot to bill a change order. That’s it. Ten minutes a week tells you more than most business owners know in a full year.

 

Step three: bill your change orders every week. Not at the end of the project. Every week. This one change alone can recover tens of thousands of dollars a year, because every time you do extra work and don’t bill it immediately, you’re basically writing a check to your client. So you need to stop donating your labor.

 

Now, here are the three numbers to watch. Number one: profit per project. Not overall. Per project. This is the number that matters. If it suddenly drops, you know something changed, and you need to go figure it out and fix it.

 

Number two: untagged spending. Every dollar that doesn’t get tagged to a project is a dollar you’re flying blind on. Keep untagged spending under 2% of your total spending. Above that, you know your data is lying to you.

 

Number three: change order billing speed. Track how fast you’re billing after the extra work is done. Target under seven days, because slow billing creates fake losses.

 

So here’s the bottom line I want to leave you with. You don’t need extra work. You don’t need to be busier. You just need to know which projects are actually making you money, and fix or drop the ones that aren’t. One simple scoreboard, 10 minutes a week, and you’ll see more profit without adding a single project to your schedule. That’s not accounting. That’s running a real business.

 

And that’s exactly what we do every day here with our fractional CFO services. If you have any challenges, drop me a comment and let me know. We’re happy to jump on a call or Zoom to discuss your challenges. Thank you so much for watching. I’ll see you in the next one.

 

This has been another episode of our tax-saving video series. If you enjoyed this video, please like it, subscribe below, and share it with other business owners. You can find previous episodes and more information at bastacpa.com. Thanks for listening, and have a great day.

Episode Insights and Action Items

1. Busy is not the same as profitable.What’s happening: You can be booked solid with the phone ringing nonstop and still have a bank account that tells a different story. That isn’t a hustle problem. It’s a profit leak problem.

2. Most contractors don’t know which projects make money.What’s happening: Most construction books run as one big pile of numbers: revenue in, expenses out. Nobody can say which project won and which one lost.

3. Your proudest job can be your money-loser.What’s happening: A $3 million firm that believed it ran at about 15% profit found its $180,000 showcase project was losing about $9,000 after labor, materials, and subs. The owner did nothing wrong. He just didn’t have a system that told him the truth.

4. Unbilled change orders are donated labor.What’s happening: Every time you do extra work and don’t bill it right away, you’re basically writing a check to your client. Slow change order billing also creates losses on paper that aren’t real.

 

ACTION ITEMS

1. Give every project its own scoreboard.Set up each contract as its own project and tag every dollar of labor, materials, subs, permits, and equipment rental to it. Could you see the profit on each job today?

2. Review your bottom three projects for 10 minutes every week.Sort your project profitability report by profit and ask one question about the bottom three: why is this one losing money?

3. Bill change orders every week.Not at the end of the project. How many days does it take you to bill extra work right now?

The Three Steps, in Plain English

Samy’s fix comes down to three steps and three numbers to watch. None of it requires new software beyond QuickBooks.

Step 1: Give Every Project Its Own Scoreboard

In QuickBooks, this is called a project. Every contract gets its own project, and every dollar you spend because of that contract gets tagged to it: labor, materials, subcontractors, permits, and equipment rental. The rule is simple. If you spent the money because of that job, it belongs to that job.

For labor, that usually means tracking crew hours by project so payroll costs land on the right job instead of a general bucket. For bills and credit card charges, it means choosing the project at the time you enter or categorize the expense, not months later.

This one change turns your books from a black box into a scoreboard. Instead of one company-wide profit number, you can see which jobs are carrying the business and which ones are dragging it down.

Step 2: Review It Every Week, in 10 Minutes

Once a week, open your project profitability report, sort it by profit, and look at the bottom three projects. Ask one question: why is this project losing money?

In Samy’s experience, the answer is almost always one of four things: labor went over, materials weren’t tracked correctly, a subcontractor added scope, or a change order never got billed. Each one has a different fix, and catching it while the job is still running is what makes it fixable.

Ten minutes a week on this tells you more than most business owners learn in a full year.

Step 3: Bill Change Orders Every Week

Bill change orders every week, not at the end of the project. When extra work sits unbilled, you carry the cost of that work on the job without the matching revenue, and the project looks worse than it really is. Wait long enough, and some of it never gets billed at all.

Samy’s view is that this one habit alone can recover tens of thousands of dollars a year for many contractors. Every unbilled change order is labor you are donating to your client.

Three Numbers to Watch

Profit per project. Not overall profit. Profit for each job. If it suddenly drops on a project, something changed, and you need to find it and fix it.

Untagged spending. Every dollar not tagged to a project is a dollar you’re flying blind on. Keep it under 2% of total spending. Above that, your data is lying to you.

Change order billing speed. Track how many days pass between finishing extra work and billing it. Keep it under seven days, because slow billing creates fake losses.

Number
Samy's target
Profit per project
Watch every job for sudden drops
Untagged spending
Under 2% of total spending
Change order billing speed
Under 7 days after the work is done

The $180,000 Project That Was Losing $9,000

This is the real client story Samy shares in the episode. The client is not named.

The owner ran a construction firm doing about $3 million a year, with a great reputation and plenty of work. Asked how profitable the company was, he said about 15%, and he was confident about it.

Samy’s team set up simple project tracking in QuickBooks. Two weeks later, the report showed that one of his biggest jobs, a $180,000 contract he was proud of, was losing about $9,000 after labor, materials, and subcontractors.

Nothing about the business was broken. The numbers just had never been split by project, so a losing job was hiding inside a company that looked healthy overall. With a weekly scoreboard, he can now see that kind of problem while the job is still running.

The project
Amount
Company revenue
About $3 million a year
Owner's estimate of company profit
About 15%
Contract value
$180,000
Result after labor, materials, and subs
About a $9,000 loss

4 Reasons a Project Loses Money

1

Labor went over

Crews spent more hours than the estimate allowed, or labor wasn’t tracked to the job at all.

2

Materials weren’t tracked right

Materials were bought for the job but recorded somewhere else, or never matched to the estimate.

3

A sub added scope

A subcontractor did extra work that raised your cost without a matching change on the client side.

4

A change order never got billed

You did the extra work, paid for it, and never sent the bill.

Bottom Line

You don’t need more work, and you don’t need to be busier. You need to know which projects are actually making you money, and fix or drop the ones that aren’t. One simple scoreboard and 10 minutes a week can show you more profit without adding a single project to your schedule.

Not sure which of your jobs are making money? Book a call with me and we’ll talk through your challenges. That’s what our fractional CFO services do every day: set up the scoreboard, track the right numbers, and help you run the business on the truth.

ABOUT THE SPEAKER

Samy Basta, CPA

Founder, Basta & Company

 

Samy has over 25 years of experience in tax strategy, financial planning, and business advisory, with particular expertise in construction, architecture, and interior design. He hosts Basta & Company’s tax-saving video series, where he explains the rules California business owners actually run into, in plain English.

Job costing means tracking revenue and every cost, including labor, materials, subcontractors, permits, and equipment, by individual project, so you can see the profit on each job instead of one company-wide number.

Set up each contract as a project, tag every expense and crew hour to the right project as you enter it, and review the project profitability report weekly, sorted by profit.

Usually it’s one of four things: labor went over, materials weren’t tracked correctly, a subcontractor added scope, or a change order was never billed.

Every week, as the extra work is done. Samy’s target is billing within seven days of completing the work, because slow billing creates losses on paper and some extras never get billed at all.

Untagged spending is any cost that isn’t assigned to a project. Samy’s target is under 2% of total spending. Above that, your project reports can’t be trusted.

Fill out our contact form to share your business details and biggest financial challenges. We’ll review everything, and if it looks like a good fit, we’ll invite you for a call to dive deeper. No obligation.

Frequently Asked Questions

Still Have A Question?

We’re here to help. Reach out to our team and we’ll get back to you as soon as possible.

Sounds like a fit? Let's talk.

Basta & Company guides San Francisco businesses through every financial milestone — from business structure and accounting systems to tax strategy and scaling with confidence.